A small terrace at a football ground comprises of 15 steps each of which is 50 m long and built of solid concrete.



Answer -

Each step has a rise of 1 4 m and a tread of 1 2 m. (see Fig. 5.8). Calculate the total volume of concrete required to build the terrace. 
Solution

As we can see from the given figure, the firststep is ½ m wide, 2nd step is 1m wide and 3rd stepis 3/2m wide. Thus we can understand that the width of step by ½ m each timewhen height is ¼ m. And also, given length of the steps is 50m all the time.So, the width of steps forms a series AP in such a way that;

½ , 1, 3/2, 2, ……..

Volume of steps = Volume of Cuboid

= Length × Breadth Height

Now,

Volume of concrete required to build the firststep = ¼ ×1/2 ×50 = 25/4

Volume of concrete required to build thesecond step =¼ ×1/×50 = 25/2

Volume of concrete required to build thesecond step = ¼ ×3/2 ×50 = 75/2

Now, we can see the volumes of concreterequired to build the steps, are in AP series;

25/4 , 25/2 , 75/2 …..

Thus, applying the AP series concept,

First term, a = 25/4

Common difference, d = 25/2 – 25/4 = 25/4

As we know, the sum of n terms is;

Sn = n/2[2a+(n-1)d] =15/2(2×(25/4 )+(15/2 -1)25/4)

Upon solving, we get,

Sn = 15/2 (100)

Sn750

Hence, the total volume of concrete requiredto build the terrace is 750 m3.

 